Energy T & D
From Poletop to 600 KVDC
Substation automation is from the smallest poletop that require a few I/O to the large installations that has PRP & HSR with redundant controllers on a fiber optic network. Brodersen has the complete solution.
Start configure your solution, and we will be happy to assist you. We do it every day 😉
Parallel Redundancy Protocol, PRP
High-availability Seamless Redundancy, HSR
Both are standardized redundancy protocols for industrial automation networks that require zero recovery time.
PRP/HSR products are suitable for electrical substation automation and mission-critical applications that cannot tolerate any system downtime.
IEC 62439-3 Clause 4 = PRP
IEC 62439-3 Clause 5 = HSR
GE Energy – uk
Project: | Power Substation Automation |
End user: | N/A |
Consultant: | GE |
Contractor: | GE |
Period: | 2020 |
Description: | Substation Automation. The project is based on RTU32M with 61850 Client and standard I/O modules |
GE Energy – Spain
Project: | Power Substation Automation |
End user: | N/A |
Consultant: | GE |
Contractor: | GE |
Period: | 2015 |
Description: | Substation Automation. The project is based on RTU32 with 61850 Client and standard I/O modules |
POWELL Industries – UK
Project: | Power Substation Automation |
End user: | BP |
Consultant: | Powell Industries |
Contractor: | Powel Industries |
Period: | |
Description: | Power substation Automation. The project is based on redundant RTU32 with 61850 Client & Server + modbus client & Server + Brodersen native Binding protocol. |
YEDAS – Turkey
Project: | Power Substation Automation |
End user: | Yedas |
Consultant: | GE (General Electric) |
Contractor: | GE (General Electric) |
Period: | |
Description: | Power substation Automation. +100 RTU’s where used for control and monitoring the substations. Up to 26 IED were connected to each Brodersen RTU32. The IED’s use 61850 and were converted to 60870-5-104 by the RTU’s before sent to YEDAS SCADA. Larger sites were above 35K variables. SNMP was used for synchronizing the substations to central SCADA. |
TEDAS – Turkey
Project: | Power Substation Automation |
End user: | TEDAS |
Consultant: | SPP ENGINEERING LTD. |
Contractor: | SPP ENGINEERING LTD. |
Period: | |
Description: | Power substation Automation. +100 RTU’s where used for control and monitoring the substations. Main protocol was DNP3 & Modbus. 61850 was not used in the project, but was implemented as for future use. |
BOTAS – Turkey
Project: | Power Substation Automation |
End user: | BOTAS |
Consultant: | SPP ENGINEERING LTD. |
Contractor: | SPP ENGINEERING LTD. |
Period: | |
Description: | Power substation Automation. +100 RTU’s where used for control and monitoring the substations. The RTU32S was used with mains protocol DNP3 & Modbus. |
Sanofi-Aventis – France
Project: | Power Station Automation |
End user: | Sanofi-Aventis |
Consultant: | N/A |
Contractor: | N/A |
Period: | |
Description: | Plant Power Automation. 34 power stations controlled and monitored by Brodersen RTU32. Task includes uptime critical requirements and sites with redundant setup. |
Alstom – Norway
Project: | Hydro Power Plant Management |
End user: | Statkraft, Norway |
Consultant: | N/A |
Contractor: | Alstom |
Period: | 2008 |
Description: | Monitoring and control of Hydro Power plant distributed in Norway. Complete plant control and regulation. Meets the high level IEC60870-5-104 Statkraft requirements with Redundancy Groups etc. RTU32 obtained KEMA approval for this application. |
Areva – Germany
Project: | 10kV Switch |
End user: | |
Consultant: | N/A |
Contractor: | N/A |
Period: | 2003 |
Description: | Monitoring and control of medium high voltage switches 10KV. Special RTU and extension modules for operation in high magnetic field environment. IEC60870-5-101 protocol via GSM. |
Cegelec – Philippines
Project: | Monitoring Power Stations |
End user: | N/A |
Consultant: | N/A |
Contractor: | Cegelec |
Period: | 2003 |
Description: | Monitoring transformer stations. IEC60870-5-101 communication using leased lines. |
N-ERGIE – Germany
Project: | Remote Metering, Transformer Monitoring & Control |
End user: | N-ergie |
Consultant: | N/A |
Contractor: | ABB |
Period: | 2001 to 2003 |
Description: | Monitoring and metering in an electricity network with more than 1,700 outstations. IEC60870-5-101 communication via leased lines. The RTUs feature a built-in interface for IEC 1107 and IEC 102 meter interface. |
RWE – Germany/Austria
Project: | Remote Metering, Transformer Metering & Control |
End user: | RWE |
Consultant: | N/A |
Contractor: | N/A |
Period: | 2002 |
Description: | Monitoring and metering of small and medium hydro-power stations in Austria via RWE-European Backbone from central host in Germany. |
ABB – Germany
Project: | Various Power Distribution Applications |
End user: | |
Consultant: | |
Contractor: | |
Period: | |
Description: |
Stadtwerke Hagen – Germany
Project: | Metering, GSM |
End user: | Stadtwerke Hagen |
Consultant: | N/A |
Contractor: | N/A |
Period: | 2001 to 2002 |
Description: | Electricity consumption metering for high volume customers. Transparent meter interface for uploading load-profile transmission and remote meter setup. More than 400 intelligent GSM modems installed. |
NPower – UK
Project: | Precipitator Monitoring |
End user: | NPower |
Consultant: | PIACS |
Contractor: | N/A |
Period: | 2000 to date |
Description: | Supply of several Bitbus gateway and optical repeater modules to monitor a number of precipitators made by PIACS in a power station situated in South East of England. |
EFT – Ireland
Project: | Energy Management |
End user: | Electricity Supply Board customers |
Consultant: | EFT – Ireland |
Contractor: | N/A |
Period: | 2002 to date |
Description: | EFT uses Brodersen’s RTUs in conjunction with their Energy Management software to monitor energy usage. EFT jointly markets their solution with the Electricity Supply Board (ESB) of Ireland. The aim is to identify where and how electricity is being used by ESB’s customers by sub-metering of appliances etc. |
Video Training
- RTU32 User Guide
- IO Module User Manual
- Online configurator
- Redundancy User Guide
- SIL-2 Guide RTU32M
- IEC 62351 understand what it is
- Remote IO
App Notes
WORKSUITE. Get all the info you need in the software or driver section.
Brodersen Worksuite (download free trial limited to 40 I/O)
Worksuite Download
Code Generator
Test Tool for 60870-5-104, 101, 104. Simulate SCADA and get to commissioning with a tested solution. Get password from sales. The test tool is not free. Our engineers has spend time on it, so you can free up yours.
60870 Test tool
RTU32M CPU
LB2 I/O DXF files
EPLAN P8 2.9 with Macro
- EN/IEC60870 Configurator User Guide
- RTU32/IEC61850 Server Presentation
- RTU32/IEC61850 Client Presentation
- RTU32/EN/IEC60870 Presentation
- RTU32 IEC60870-5-101 Interoperability doc
- RTU32 IEC60870-5-104 Interoperability doc
- RTU32 DNP3 Slave Device Profile
- OPC UA User Guide
- Siemens S7 Client User Guide
- Getting started with 61850 Client