From RTU Configuration to Deployment: Building a Better Engineering Workflow

Five stage RTU engineering workflow from specify to operate, with the handoffs between stages marked

Ask an engineer where an RTU project loses time and they will rarely name a stage. Specifying the hardware is a known exercise. Writing the logic is a known exercise. Commissioning is hard but predictable. The time disappears somewhere less obvious: in the gaps between those stages, where the same information gets written down again in a different place, by a different person, in a different format. Improving the RTU engineering workflow is mostly about closing those gaps.

The five stages, and the four handoffs

Five stages: specify, engineer, test, commission, operate, with handoff markers between each

Each marker in that diagram is a transfer. Someone finishes a stage and hands the result to whoever does the next one. That transfer is almost never a clean export. It is usually a spreadsheet, a document, a verbal briefing, or a combination of all three.

What actually gets re-entered

The clearest way to see the cost is to follow one piece of information through the project.

Table showing how the point list, tag names, scaling, site changes and the working configuration get re-entered and drift

None of this is carelessness. Every one of those steps is reasonable on its own. The problem is cumulative: by the time the site is running, there are several versions of the truth and no agreed authority among them.

Where it bites, and it is usually later

A project can absorb all of this and still be commissioned successfully. The cost arrives afterwards, which is why it rarely gets attributed to the workflow.

  • The first modification. Eighteen months later someone needs to add two signals. The question is not how to add them, it is which document to trust about what is currently there.
  • A device failure. Replacing the hardware is quick. Restoring the exact configuration it was running is only quick if someone kept a current copy.
  • The second site. A near-identical station gets engineered close to from scratch, because nothing from the first one was captured in a reusable form.
  • The handover. The engineer who knows the quirks moves on, and a large part of the project’s real documentation leaves with them.

The commissioning week nobody plans for

The gaps become visible on site, usually in the same way. An engineer arrives with a configuration that was correct when it left the office. The plant has moved on slightly: an extra signal was added during construction, a valve is a different model, two cables are swapped relative to the drawing.

None of that is unusual, and a competent engineer works through it. The issue is what happens to those decisions. They are made at the panel, often at the end of a long day, and they go straight into the device. The spreadsheet in the office still describes the original design. The as-built document, if it gets written, is reconstructed later from memory.

So the site works, and the record of why it works does not exist anywhere complete. Most of the cost of a weak workflow is paid in that week, and collected quietly over the following years.

Five changes that close the gaps

1. Let the specification produce the build

The further the gap between “what we decided” and “what was ordered”, the more chance of a mismatch discovered on site. Using the RTU Configurator to work through I/O, protocols, power and mounting produces a build that fits together, and a configuration you can hand to the next stage rather than a list of assumptions.

From there the engineering happens in WorkSuite, with wizards for local and remote I/O, communications interfaces, logic programs, data handling and the operator interface. The logic itself is written in ladder, function block diagram or structured text, and converts between them, so the application is not locked to whichever language the original engineer preferred.

2. Define the tag once, not once per protocol

This is the single biggest source of drift, and it is also the most fixable. In Brodersen WorkSuite, the RTU engineering software, you define tags that link I/O and program data to the protocols, and one tag can be used by several protocols at once.

That matters more than it sounds. If a site reports to a SCADA master on IEC 60870-5 and also publishes to another system on Modbus or DNP3, the signal is defined once and exposed to both, rather than being entered separately for each and quietly diverging. The point list stops being several documents that need reconciling and becomes one definition with several outputs.

3. Test before site, properly

A fault found on the bench costs an hour. The same fault found during commissioning costs a visit, and sometimes an outage window that is hard to get back.

Brodersen provides a 60870 Test tool that simulates a SCADA master, so the application can be exercised against a simulated control system before anyone drives anywhere. That is the cheapest hour in the whole project, and it moves the discovery of problems from the panel to the desk.

4. Start from a template, and read the truth back from the device

Two WorkSuite habits remove most of the repeat work. Project templates mean the second similar station starts from the first one rather than from a blank page. And Upload from RTU reads the module list and configuration back off a connected device, so the as-built state can be taken from the thing itself rather than reconstructed from memory.

That second one is the practical answer to the commissioning problem above. If the site was changed at the panel, you can retrieve what it actually ended up as, instead of relying on whether somebody remembered to write it down.

5. Hold the operating state centrally

Once the site is live, the engineering question becomes an operations one. Odin’s Eye keeps configuration templates, per-device program backup, firmware versions and an event log centrally, so the state of a site is a record the organisation holds rather than something that lives on one laptop.

WorkSuite builds and commissions it. Odin’s Eye keeps track of it afterwards. The handoff between those two is the one worth getting right, because it is the one that lasts for the next decade.

What to agree before the next project starts

None of this needs a transformation programme. It needs five decisions made once, before the next project rather than during it.

  • Which document is authoritative for the point list, and who is allowed to change it. One name, one location.
  • A tag naming convention, written down, applied from the specification stage onward rather than invented per site.
  • Where scaling is applied, at the device or at the SCADA end. Pick one and be consistent, so nobody applies it twice.
  • How site changes get written back, and by when. A rule that says “before the engineer leaves site” works. A rule that says “when there is time” does not.
  • Where the working configuration is held, centrally, so recovering a failed device does not depend on finding a particular laptop.

Agreeing those five costs an hour. Not agreeing them costs a little on every project, forever, and the cost never appears as its own line.

Design the workflow for year five, not week one

Most engineering workflows are optimised for getting the first site live. That is understandable, because that is what the schedule is measured against. But an RTU installed today will be modified, diagnosed, updated and eventually recovered over ten to fifteen years, by people who were not involved in building it.

A good test when choosing how to work: if the engineer who commissioned this site left tomorrow, how long would it take someone else to understand it and change it safely? If the answer is uncomfortable, the gap is not in anyone’s skill. It is in the workflow.

The stages of an RTU project are well understood. The handoffs between them are where the hours go and where the errors enter. Specify in a way that produces the build, define each tag once rather than once per protocol, test against a simulated master before site, start the next station from a template, and hold the operating state centrally. None of those are heroic. They are just decisions made before the project rather than during it.

Explore WorkSuite → Start in the RTU configurator →

Conclusion - enjoy having a 'future proof' RTU...
Your RTU requirements will evolve over time, so when you need more I/O, comm ports, protocols or RTU functionality - know it can be easily implemented in a Brodersen RTU.
Slide Heading
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
Click Here

Newsletter